Tag Archive for 'kitchen'

02
May

F minus 4

Four days ’til our final inspection. Our last two tradesmen (for phase 1A) were out today–masonry and HVAC.

Kevin McKeever is our mason. He came out yesterday to salvage as many of the old bricks from our original chimney as possible. This morning he and his assistant built the chimney up about seven feet, installed the counter-flashing and chimney cover/spark arrestor. They mixed the old bricks in with new ones, and it blends very nicely.

Our new chimney

José Miranda (of Alpha Services) is our HVAC contractor. He came out today to install the A/C condensor–I was surprised at how much work was involved in this process! The copper pipes between the attic and the condensor were filled with nitrogen, soldered, evacuated, then filled with refrigerant. The unit is powered by a 40 amp circuit and code requires a power cutout box, so: mount the cutout box to the wall, wire the circuit up to one side of the box and the unit to the other side. The control circuit was wired to the condensor (outside) and the FAU (in the attic). Finally, José tested everything. (IIRC, testing alone took most of an hour.) For the first time since this house was built 60 years ago, it now has central heating and air conditioning. The weather is too mild for either heating or cooling right now–it’s about 72°F, so I guess we’ll have to wait for a heat wave to really test the A/C.

José installing the condensor

Meanwhile I’ve been busy myself. I got the dishwasher bolted into its cabinet last night. It was a lot tougher than I thought it was going to be, because I couldn’t get the darn thing plumb and level. I finally realized that either the power or water line wasn’t in its proper place, so when I tried to lower the back of the unit it was getting stuck on the water or electrical line. We pulled the unit all the way out of the cabinet, taped both the water and power lines in place on the back of the unit, and slid it back into the cabinet. After that the adjustments were easy, although the cabinet opening is just a little too short (maybe 1/8″) for us to get the dishwasher perfectly plumb. But it’s pretty darn close.

Our dishwasher

I also got one of the attic fans finished. The other one is mounted in the gable, although it’s currently wired with a temporary appliance cord. The important thing is that they both work. They’re keeping the attic much more tolerable and extending the time I’m able to work up there. I should have no trouble finishing the other tasks in the attic this weekend.

Final inspection punch list:

  • Install smoke alarms. The wiring is done, except for power feed. Other than that, all I need to do is put up the ceiling mounts and attach the smoke alarms.
  • Install fluorescent lights in the kids’ closets. Wiring is done, just need to put the fixtures on the walls and hook them up.
  • Finish installing second attic fan.
  • Finish wiring and test the whole-house fan.
  • Clean up the light- and switch wiring for the attic lights.
  • Wire and install ceiling light in entry.
07
Mar

Remodel update

I’ve been pretty busy at work and home since Christmas, and I can’t find the USB cable for our camera. Both things have kept me from blogging as much as I would like, especially regarding our remodel. But a few things have happened recently that are definitely worth posting.

First, we’ve finished our new bathroom! (Why is this a big deal, you ask? Because I share this house with my wife and two teenage daughters. Having two bathrooms is HUGE news!) Our plumber was out about two weeks ago and finished hooking up the shower/bath and the toilet. And I finally got all the vanity outlets, lights and switches wired up, along with the exhaust fan. I still have one fluorescent can light in the ceiling that’s burned out two tubes within a few months, which I need to investigate.

Second, our cabinet maker got all the trim and touch-up work done on the cabinets and installed the foot rail under the bar. (Here’s where I’d really like to insert a few pictures. Why in the heck did Kodak have to use a proprietary cable on their camera?!?) He also got the under-cabinet lights working reliably–looks like they were drawing too much power, so he installed some lower wattage bulbs. The lights haven’t given us any trouble since.

Third, our big fancy stove is finally 100% operational. (The two “extra low” burners hadn’t worked since we installed it back in December.) It took the service company four visits (and 3 parts orders), but they finally got it working on Tuesday.

That’s all the big news. I also updated the punch list and got to mark two rooms (the new bathroom and the nook) as “complete”. There are also some rooms/areas that are very nearly finished: entry, great room, kitchen, laundry/utility room, bedroom hallway, and the kids’ bedrooms. We still have quite a bit of work to do in the game room (the old dining room), garage, attic, and the exterior of the house.

We still a lot of work ahead of us, but the house is getting more and more comfortable. :)

23
Dec

Christmas break

I’ve got a week and a half off for Christmas, and one can only socialize so much. We’ll be spending considerable time working on our remodel, of course.

Speaking of the remodeling project, I noticed that I haven’t post much this week. I’ve been busy at work, getting everything done before the year-end shutdown. We’ve also had quite a bit going on at home!

  • Our plumber has the kitchen sink, disposal, and dishwasher working–hooray! He’s also done most of the work in the new bathroom, although two small parts have gone missing so our new shower and toilet aren’t hooked up yet. But he did get the vanity sinks plumbed, which is significant because one of those sinks receives the furnace condensate — No more toting 5-10 gallons of water out every day! (And no more mopping up when I forget to empty the bucket. :| )

  • Rick, our tile setter, has finished his work. In fact, he grouted the entry about an hour before my wife’s office party started on Friday night. His work is fantastic, just like last time. He has some small touch-up work to do after the holidays, and we still have to seal all the floor grout and the shower.

  • Don and J were out this week and took care of a whole bunch of stuff — hanging doors, installing vanity cabinets, building landings and stairs for the exterior doors, etc. Don’s still got to come back and finish installing the medicine cabinets in the bathroom and re-hanging Caira’s bedroom door, but the door got a bit warped and we’re still waiting for it to get flattened out.

Between our trades’ work and our own, we’ve very nearly finished our kitchen. This truly is the “heart of the home”, especially for our family. Barb and I are both pretty competent and enthusiastic cooks, and our teenage children are heading down the same path. So it was more or less inevitable that we would focus our finish-work effort on the kitchen first. The punch list for this room is now quite short:

  • Eric (cabinetry)

    1. Trim cabinet openings for dishwasher and wine frig.
    2. Crown molding around hood chimney.
    3. Re-install scribe along range backsplash.
    4. Install baseboard.
    5. Install foot rail along bar.
    6. Adjust several doors and drawers which aren’t closing properly.
  • Rick (tile)

    1. Replace two pieces of cracked bullnose skirting.
    2. Install bullnose piece between bar top and cookbook shelves.
  • Us

    1. Hang the pot rack.
    2. Install two pendant lights over bar top.
    3. Wire up the blower for the range hood.
    4. Push the range back flush to the wall (fiddle with gas supply hose).
    5. Clean the floor and seal the grout.
    6. Move refrigerator into its cabinet.
    7. Adjust wine frig and dishwasher (once Eric is done).
    8. Run the water line for the ice maker and filtered water tap.

Our tradespeople are gone for the holidays, but I expect to finish at least half of the “Us” list today. Our camera batteries are dead, so perhaps Barb can pick up some fresh ones today and I’ll do a follow-up post on our progress, complete with pictures.

17
Dec

More appliances…

Our hood is wired up, so we have lights on our fancy new range!

100_0850.JPG

I was so pumped about the range in my earlier post that I forgot to mention that we got our washer and dryer hooked up again. Being able to do laundry at home is another one of those things that people take for granted. (Hmm, I think I’m going to have to do a post on that theme.)

100_0851.JPG

16
Dec

We have a stove!

At long last, our range is installed! Barb didn’t waste any time putting it to use.

100_0847.JPG

We’ve got the hood mounted to the wall, but it’ll be few days before that’s hooked up. Our HVAC installer will be out on Tuesday or Wednesday to finish the ducting, and I should have the power hooked up later tonight. (At least the lights will work, even if there’s no point in running the fan.)

13
Dec

Wed. progress

Louie, who did our gutters, came by yesterday and installed the last of our downspouts. Rick was also out yesterday afternoon and got the kitchen tiled, including all the appliance bays. Lots of finicky corner- and edge cuts, plus he had to deal with the floor transition. When Barb and I got home, we spent some time discussing tile designs for the entryway with him. Between the fiddly tile work, the time we spent talking, and the fact that we didn’t come to a decision on the design, the entry didn’t get tiled last night.

100_0822.JPG

No worries, though. Rick is going to have one of his guys out today to grout the floor tile that’s been installed so far, (about 90% of the total). Priority areas are:

  1. Laundry/utility room — We really want to be able to do laundry at home again!

  2. Bathroom — One of the chores that’s beginning to annoy me is dumping the water from our condensing furnace. Once the bathroom tile is grouted, we’ll be able to install the vanity, and then we’ll be able to plumb the condensation line into the drain system. No more hauling 5-gallon buckets of water, hooray!
    100_0825.JPG

  3. Kitchen — We’ll be able to install some of our appliances once the kitchen floor is grouted, although we’ll still have to wait for the backsplash grout before we can bring in the new range.

Looks like we’ve got a busy weekend coming up. We’ll be putting in baseboard behind some of the appliances (like the refrigerator), and installing as many of the appliances as possible. If the backsplash in the kitchen is grouted by Friday, we should have or kitchen up-and-running over the weekend. w00t!

07
Dec

Kitchen faucet’s outta here!

We got our faucet out of the kitchen finally. The guys are plugging the hot- and cold water and sewer lines right now. We’ll cover it up and I’ll post some pictures when we’re all finished.

Posted via Jott

Pictures are up!

100_0697.JPG 100_0714.JPG 100_0715.JPG 100_0754.JPG

30
Oct

We passed!

We passed frame inspection! Woo hoo!

Lots of things are going to happen pretty quickly, now. Insulation goes in tomorrow (Wed). Drywall starts Thursday. Our plumber and HVAC people are also scheduled to be on-site Thursday to hook up the gas and fire up the furnace, respectively. (We need to have heat for the drywall tape and texture, which is scheduled for all of next week.) Our cabinet maker has already finished our cabinetry, so he’ll bring them down from his shop late next week or on Monday, Nov 12. Of course, this project wouldn’t be complete without at least one major scheduling glitch: our tile guy is going on vacation for two weeks, starting on Nov 14. We’re trying to work something out between the tile setter, the cabinet maker, and the drywall crew, to see if we can get the kitchen sink and counter tops done before the tile setter starts his vacation.

All the stuff above is being done by tradespeople. In the meantime, we have a few things to do as well. Tonight we need to prep for insulation, so all the exterior walls, (including between the house and the garage), need to be cleared and any outstanding wiring issues need to be finished, (e.g. telephone/network wiring, running the few remaining branch circuits into the breaker box). Wednesday night we need to make sure that the entire house and garage are completely empty, so that drywall can be delivered in each room and installed on Thursday morning. We’ll need to pick up a pair of high-efficiency filters for each of the HVAC returns by Thursday afternoon, so that our furnace doesn’t get ruined by drywall dust. This weekend (probably Saturday) we’re going to meet with our tile setter and figure out how many tiles need to be bullnosed in which direction(s), so we can get that started next week. Once we’re ready for tile, I think we’ll resume working on Barb’s quilt studio.

The end of our project is looking a little closer… Well, the end of phase 1, at least.

15
Oct

39 days til Thanksgiving

Barb took a couple of well-earned days off from our remodel and went to the Pacific International Quilt Festival with my mom on Friday and Saturday. But I wasn’t working alone–J and Andre did a bunch of work for me on Saturday. Major accomplishments were framing the old doorway in the kitchen and sheathing the west gable, which is generally the windward side of the house so the place has been a bit warmer. They also framed the attic access in the garage. While they were framing, I got started on the kitchen wiring.

Barb got back on Saturday night, and she and I worked all day on Sunday. Barb (with some help) pulled the old window air conditioner out of the wall in the front room, then framed in the hole left by the A/C, insulated and sheathed it. She also got most of our crawlspace vent covers nailed in place. Meanwhile I got most of the kitchen wiring done.

The original west wall will be insulated tomorrow, and Barb and I will sheath the wall in the evening. (It’ll be nice having the drywall covered again, now that the rainy season is here!) Andre and J are supposed to be back on Tuesday or Wednesday (or both) depending on the weather. I need to finish wiring the front porch so they can sheath that gable, so I guess that’s my other priority for Monday night. Lots to do this week if we are going to try for our framing inspection, so it may be time for me to take some more time off from my day job…

12
Oct

Remodel/addition at six months

Construction started on our remodel/addition project six months ago, today. We were hoping to be finished by now, but at least the end is in sight! I’m almost done with the wiring (finally!), and we’re just about ready to jump our next major hurdle–rough frame inspection. Once we’re past that, we’ve got about four weeks until our kitchen is operational, so we ought to be able to host Thanksgiving this year. Hooray!

I haven’t been posting many pictures, either here or on our flickr remodel collection–either I can’t find the camera when I need it, or (more typically) I’m just too busy to shoot any pics. Yesterday was an exception. We had our GC send out a crew to finish some of the framing yesterday, and I managed to get some photos of (what’s left of) our kitchen:

100_2072.JPG 100_2074.JPG

I also managed to get a picture of the laundry/utility room before the doors were installed:

100_2075.JPG

The stucco foreman came out to look at the project yesterday. He gave us a rather long list of things that needed to be taken care of before he could put up the lath. :( But the good news is that he had his crew set up the scaffolding early so that we could use it to finish sheathing our gables. (That’ll be much easier than hauling sheets of plywood up a pair of ladders!)

Work remaining before rough frame inspection:

  • (us) Finish rough electrical–mostly the kitchen, which I can start now that the kitchen framing is done;
  • (plumber) Finish rough plumbing–water heater T&P hookup, utility sink vent reconnected;
  • (us) Take care of the issues listed by the stucco foreman;
  • (insul.) Insulate the original west wall of the house (insulation crew is scheduled for next Monday);
  • (us) Sheath the wall after insulation is installed (rain forecast for Tuesday, so Barb and I will do this Monday evening);
  • (us) Sheath the rest of the gables (after rough plumbing is finished);
  • (stucco) House wrap and lath for stucco.

We’ve got a busy weekend ahead of us! But hopefully we can be ready for our rough frame inspection by late next week, which would leave us five weeks until Thanksgiving. It’ll be close, but I think we can make it.




November 2008
M T W T F S S
« Oct    
 12
3456789
10111213141516
17181920212223
24252627282930

Tags

abramoff accessibility acetylene activism aerial photo afrofunk aim4tree air america airport express alite alito amtrak andante andy anti failure any browser apache apple applescript arden arcade arden park ariana arnold ashland astronomy attic attika audio avid reader backup baen bart bathroom bbq bee beef begonia bgg bike bike hikers bike journal bikejournal biketalk bill oreilly bittorrent blacklist blog bloggercode blogroll blueberry boardgamegeek boardgames bonjour book bookcrossing boot failure bootcamp borderline chaos bugmenot bush business card cabinetry caira caitlin california candamir caroline carpet cat cateye cdrom celebration cellular phone century cheese chicken chico chimney chinese chipotle chocolate christmas chumby city bikes civilization cjd claire club club fed co op coconut coffee comfort food community computer concord congress conquest conservation consumer reports copyright costco crazybikerchick crepe crock pot cruftbox css csus curl currency custard cvntrak dagoba daniel goetz darwinports datarescue date format death delicious monster democracy now Democrat demolition dessert dickens diff disaster discrimination discworld dishwasher diskwarrior dixie belle dock doors downing street memo drm dryer drywall dump ed burke eff eggs eject election electric car electric truck electrical electricity elvgren email energy efficiency eric meyer esr etext euthanasia facebook family faq faux news feed feedreader fence finder firefox first4internet first amendment fishmeal flash flickr flooring foreign exchange foundation fox and goose framing freebsd freedback fyq garage garden geek geotag geourl gnutar go gonuls google google earth google maps gpl gracenote graywater greek green group concat gtd gunthers gutters gwbush gymnastics hacking halloween handspring hardwood harry potter headmeta high speed photograph high tech inv hoax hobbies hobby hodgins holiday holly home power magazine horcrux houseblogs how to html humor hvac ilovejackdaniels impeach inspection insulation intel internet ipod ipodder iq iraq isight itunes ivins iwantsandy java city javascript joint chiefs joseph jott journalized blue judges cup kctc khs kimkerry kitchen kyocera la salles la times labor landscape laundry law leatherbys legal lego leopard lhc liberal library linkedin ljurban lodi logic logo lungren maaloufs mac macbook mailinator malware map marin markdown mason media media clip media reform meetup metric mexican microsoft mike comfort military milonic mindstorms mlk model railroading modoc hall monterey morning sedition motorcycle movie moving munchkin murray mushroom music mynetflix mysql naked lounge nerd score netflix network new urbanism new year New Yorker nofollow nutella oatmeal obama obcz occidental occupation omni openssl oracle organic osx owp paint pair palast palm panasonic parallels party patch peak adventures peak oil pear pedestrian village perl petaluma php ping pingback pingomatic pingomation pingqueue pirate pl sql planet bike plasma playroom entertainment plugin plugin:preview theme plugin:text control plugin:ultimate tag warrior plumbing podcast podsite politics portupgrade potato powerbook printer programming project gutenberg pryde punk puzzle qiana quilt quilt shop quiz quote r5 records racism radio railroad recent comments recipe redalt remodel resaurant resolution restaurant restore review richmond rio americano robotics roger niello ron montana roof rootkit rss sacbee sacog sacramento sacramento spotlight magazine salad san francisco sandwich santa cruz scam scandal school days scplugin security session report shakespeare shuffle sigma siriradha sitemap snl snopes social social network software soma somafab sonicchicken sonicchicken blog sony spam spam karma spellcheck spinach spirit spoiler etiquette spring hill cheese sql sqlserver stairs standards statcounter stephen king stop loss stucco stunt subversion sudoku superbowl superhero supreme court sushi svn sysadmin tacoma tags plugin takara technology telephone television template terms and conditions textcontrol thai kitchen thanksgiving theater theme theme:borderline chaos theme:elvgren theme:elvgren wordpress google code theme:fluid blue theme:fullwidth theme:head theme:journalized theme:journalized blue theme:psycho theme:redoable theme:sharepoint like theme:simple green theme:spirit theme:steam theme:wuhan theme:yadda theme switcher thomas tigris euphrates tile tinfoil hat toc tofu tower theater training transit transit oriented development tribute u haul uneasy rhetoric university village van zant veterans day video vie viking hobby vote smart w3c wall warboss washer washington post weather web web developer web server wikipedia windows wishlist woodworking wordpress workplace wpblacklist wpgatekeeper wsj yaaarr yard