Tag Archive for 'remodel electrical'

06
May

“Final” inspection today

We have our “final” inspection on the house/addition today. I don’t expect that we’ll pass on the first try, since nobody else I know has been able to pull that off. The final inspection punch list is empty for now, but Chris (our inspector) will probably give me a list of things to fix once he’s had a look around.

I still have some non-inspection work to do–things like door- and window trim, telephone/network wiring, hanging some (plug-in) fluorescent lights in the garage, etc. I also want to install two “extra” smoke alarms in the front rooms of the house. These aren’t required, but it just seems sensible to have these in every room, (except places where they’ll be sounding false alarms–the kitchen, bathrooms, laundry room). The wiring is installed for these, and I have the smoke alarms, but I can’t find their wiring harnesses or mounting rings. :\

Sadly, I’m probably going to have to stop working on the house for a while. Our permit for Barb’s quilt shop will expire in mid-June, unless I can get it inspected before that time. There’s not a whole lot of work left to be done before the next inspection (rough frame and electrical):

  • Stucco/siding transitions (east and west sides)
  • Rough-in exterior lights (6)
  • Re-flash windows
  • (McCann) Exterior lath, stucco prep
  • Fix bowed stud on south side of building
  • House wrap south side of building
  • Rough-in spotlights for design wall
  • Rough-in ceiling lights (T8 fluorescent tubes), switches (2 banks, 3-way switches)
  • Rough-in wall outlets (5, including two 4plex)
  • Rough-in ceiling fans (2)
  • Compressor closet: outlet (dedicated), overhead light, switch
  • Compressor plumbing
05
May

F minus 1

Final inspection is tomorrow! Our attic fans are both permanently installed, and the attic is relatively comfortable except from late afternoon until nightfall.

The whole-house fan is wired, tested and operational. Our new fan is a 2-speed unit, whereas our old one had three speeds. We rarely used the medium speed on our old fan, so I guess this isn’t a great loss. The new fan seems quieter on the high speed but a bit noisier on low speed, compared to the old fan. (A net “win” I think, since only the high speed was ever much of an annoyance.)

I got the kids’ closet lights installed and managed to slice up my hands pretty well. (These are surface-mount fluorescent fixtures, lots of sharp metal edges.) I’m glad that I had the foresight to put 2×4’s in the closet headers where the fixtures get screwed to the wall. No drywall anchors–they’re screwed straight into cripple studs, so the fixtures are rock solid!

The required smoke alarms are installed. I have two more that I’m going to install, but they’re not required for inspection so they go to the bottom of the list.

I’ve got to go to work today, but I’m off tomorrow for the inspection. I still have a few things to do tonight and/or tomorrow morning:

  • Clean up the light- and switch wiring for the attic lights.
  • Wire and install ceiling light in entry.
  • Run power to the smoke alarm network. Install two “extra” smoke alarms, time permitting.
01
May

F minus 6 and counting…

Final inspection in six days! Over a third of the items on the final inspection punch list got done today. (Unfortunately none of the attic work got done.) I have to go to work tomorrow, so I’ll probably only get one or two things done in the evening. But I’ll be at home again on Friday or Monday (depending on our HVAC contractor’s schedule). Either way, that’ll give me a 3-day weekend to finish everything else.

Work to be done:

  • Install smoke alarms. The wiring is done, except for power feed. Other than that, all I need to do is put up the ceiling mounts and attach the smoke alarms.
  • Install fluorescent lights in the kids’ closets. Wiring is done, just need to put the fixtures on the walls and hook them up.
  • Bolt the dishwasher into its cabinet.
  • Finish installing both attic fans. (Each about half done already.)
  • Finish wiring and test the whole-house fan.
  • Clean up the light- and switch wiring for the attic lights.
  • Wire and install ceiling light in entry.
  • (sub) Kevin (the mason) will be out Friday this week to extend the chimney to the required height.
  • (sub) José will install the A/C condensor on Friday or Monday.

Here’s what happened today:

  • Install the last few (5) switch- and outlet covers (utility room and garage).
  • Install last two exterior outlets and weather-proof covers (front porch and outside the new bathroom).
  • Install final two exterior lights (outside the back door).
  • (sub) Patch the ceiling in old bathroom hallway.
  • (sub) Pour the concrete pad for the A/C condensor.

Now that the ceiling is closed up, we’ll be able to use our new whole-house fan (as soon as I finish wiring it). The weather has cooled off again, (I don’t know if it even hit 70°F/20°C today), but it will certainly warm up again in the near future. With our old fan we used to get by quite comfortably up to about 95-100°F, and that was without insulation! It’ll be interesting to see how hot it gets before we can’t stand it and have to turn on the air conditioner.

30
Apr

One week ’til final inspection!

We have about one week left before our “final” inspection. (Final in quotes because I haven’t heard of many people who pass their first “final” inspection.) Our punch list is still fairly long, but many of those items aren’t required for inspection, e.g. baseboards, window trim, etc. Here’s what needs to be done during the next seven days.

  • Install smoke alarms. The wiring is done, except for power feed. Other than that, all I need to do is put up the ceiling mounts and attach the smoke alarms.
  • Install fluorescent lights in the kids’ closets. Wiring is done, just need to put the fixtures on the walls and hook them up.
  • Bolt the dishwasher into its cabinet.
  • Install the last few (5?) switch- and outlet covers in the utility room and garage.
  • Install last two exterior outlets and weather-proof covers, on the front porch and outside the new bathroom. (Wiring already done.)
  • Install final two exterior lights, outside the back door. (Wiring already done.)
  • Finish installing both attic fans. (Each about half done already.)
  • Finish wiring and test the whole-house fan.
  • Clean up the light- and switch wiring for the attic lights.
  • Wire and install ceiling light in entry.
  • (sub) Patch ceiling in bathroom hallway. Don and J will take care of this in the morning.
  • (sub) Don and J are also going to pour the concrete pad for the A/C condensor tomorrow.
  • (sub) José will install the A/C condensor on Friday or Monday.
  • (sub) Kevin (the mason) will be out Thursday or Friday this week to extend the chimney to the required height.

I’ll be home tomorrow since Don and J will be working, so I’m going to try to finish the attic work in the morning before it gets too hot. (Plus, once the attic fans are both running that will help control the temperature in the attic.)

07
Mar

Remodel update

I’ve been pretty busy at work and home since Christmas, and I can’t find the USB cable for our camera. Both things have kept me from blogging as much as I would like, especially regarding our remodel. But a few things have happened recently that are definitely worth posting.

First, we’ve finished our new bathroom! (Why is this a big deal, you ask? Because I share this house with my wife and two teenage daughters. Having two bathrooms is HUGE news!) Our plumber was out about two weeks ago and finished hooking up the shower/bath and the toilet. And I finally got all the vanity outlets, lights and switches wired up, along with the exhaust fan. I still have one fluorescent can light in the ceiling that’s burned out two tubes within a few months, which I need to investigate.

Second, our cabinet maker got all the trim and touch-up work done on the cabinets and installed the foot rail under the bar. (Here’s where I’d really like to insert a few pictures. Why in the heck did Kodak have to use a proprietary cable on their camera?!?) He also got the under-cabinet lights working reliably–looks like they were drawing too much power, so he installed some lower wattage bulbs. The lights haven’t given us any trouble since.

Third, our big fancy stove is finally 100% operational. (The two “extra low” burners hadn’t worked since we installed it back in December.) It took the service company four visits (and 3 parts orders), but they finally got it working on Tuesday.

That’s all the big news. I also updated the punch list and got to mark two rooms (the new bathroom and the nook) as “complete”. There are also some rooms/areas that are very nearly finished: entry, great room, kitchen, laundry/utility room, bedroom hallway, and the kids’ bedrooms. We still have quite a bit of work to do in the game room (the old dining room), garage, attic, and the exterior of the house.

We still a lot of work ahead of us, but the house is getting more and more comfortable. :)

30
Oct

Rough frame re-inspection today

(Update: I forgot to include the pictures. Doh!)

It’s been a while since I’ve posted–too busy working on the house to write much about it!

100_0448.JPG 100_0450.JPG

The stucco crew was out last week and got the house wrapped and lathed. (And incidentally gave me a ton of things to do in order to minimize future water damage. Great advice, things that needed to be done, but it burned up a lot of the time I had planned to use for wiring.) We got dinged for $800 for re-flashing all the windows. Turns out that the flashing along the bottom of the window was supposed to be left loose/flapping, i.e. only peel the top inch or two from the adhesive, so that the waterproof paper could be slipped under the flashing. So the stucco guys put new flashing along the bottom of all the windows while they were wrapping the house, and because of that they had to also flash the sides and top of the windows. (It’s just like the roof, you have to work from the bottom to the top.) Here’s a picture of the shop, without paper, to show the original window flashing:

100_0449.JPG

I got most of the wiring done while I was on “vacation” last week, so we called for our rough frame inspection last Friday. And we finally failed an inspection. :( It was Chris, our regular inspector (yay!), but he busted me righteously for not having all of my grounding wires tied together. (I thought we could just leave the wires in the boxes and make up all the connections after drywall. I was wrong.) He also nailed the contractor for omitting sheetrock nailing blocks around the bathtub and lack of insulation “dams” at the eave vents. (According to the contractor, the insulation people usually put these in before they start blowing in the insulation.)

The contractor sent out a couple of guys to take care of the insulation dams and the bathtub framing issues yesterday, and I spent the weekend and yesterday afternoon/evening tying all my ground wires together and generally making the wiring look neat and tidy. We’ll get a re-inspection sometime today, and hopefully we’ll pass this time around!

Assuming that we do pass, insulation is scheduled for tomorrow, and drywall will be installed Thursday and Friday. Taping and texturing will take up all of next week (Nov 6-10). Cabinets will be installed on the following Monday. Countertop tile installation will begin that evening or the next day and should be completed by Nov 17, and we’ll work around the tile guy to install our appliances. I doubt that we’ll be able to get our tile flooring in before Thanksgiving (Nov 22), but I’ll let the tile installer make that decision when the time comes. But it looks like our kitchen will be functional for Thanksgiving this year!

19
Oct

Inspection woes

Normally I’m very supportive of the Sacramento County Building Department. Nearly everybody I’ve dealt with has been helpful, professional, and even pleasant. On top of that, the inspector who’s assigned to our job is outstanding. But he must be on vacation or something, because today I had my first less-than-positive interaction with somebody from the building department.

Enough about that. It doesn’t even warrant a post on its own, so here’s the important news. Our gable vents finally arrived, so we can finish the three “showpiece” gables! (The one over the entry and the two in the back yard.) We are going to finish prep work for lath this weekend so that the stucco crew can come in on Monday and get the house wrapped and lathed. They’ll be finished by Tuesday evening or Wednesday some time. While they’re doing that, I’ll be finishing the electrical rough-in. Once both the electrical and lath are done, we’ll call for our rough frame inspection. Insulation will go in the walls the day after frame inspection, (assuming I remember to call them back and confirm!) The day after that, drywall starts. Drywall delivery is scheduled for next Friday morning at 7:00, so the house and garage will need to be completely cleared out by then. If we’re super lucky the drywall will be up, taped and textured by the end of the following week (Nov 2).

Just to make sure this weekend is extra fun, we’re driving to Napa (1.5 hrs) tomorrow for Caitlin’s gymnastics meet (4.5 hrs), after which we will be going down to Oakland (1 hr) my cousin’s housewarming party (who cares how long, it’s a party!), then driving back to Sacramento (1.5 hrs, designated driver presumed). So enough blogging, I’ve got way too much to do!

15
Oct

39 days til Thanksgiving

Barb took a couple of well-earned days off from our remodel and went to the Pacific International Quilt Festival with my mom on Friday and Saturday. But I wasn’t working alone–J and Andre did a bunch of work for me on Saturday. Major accomplishments were framing the old doorway in the kitchen and sheathing the west gable, which is generally the windward side of the house so the place has been a bit warmer. They also framed the attic access in the garage. While they were framing, I got started on the kitchen wiring.

Barb got back on Saturday night, and she and I worked all day on Sunday. Barb (with some help) pulled the old window air conditioner out of the wall in the front room, then framed in the hole left by the A/C, insulated and sheathed it. She also got most of our crawlspace vent covers nailed in place. Meanwhile I got most of the kitchen wiring done.

The original west wall will be insulated tomorrow, and Barb and I will sheath the wall in the evening. (It’ll be nice having the drywall covered again, now that the rainy season is here!) Andre and J are supposed to be back on Tuesday or Wednesday (or both) depending on the weather. I need to finish wiring the front porch so they can sheath that gable, so I guess that’s my other priority for Monday night. Lots to do this week if we are going to try for our framing inspection, so it may be time for me to take some more time off from my day job…

12
Oct

Remodel/addition at six months

Construction started on our remodel/addition project six months ago, today. We were hoping to be finished by now, but at least the end is in sight! I’m almost done with the wiring (finally!), and we’re just about ready to jump our next major hurdle–rough frame inspection. Once we’re past that, we’ve got about four weeks until our kitchen is operational, so we ought to be able to host Thanksgiving this year. Hooray!

I haven’t been posting many pictures, either here or on our flickr remodel collection–either I can’t find the camera when I need it, or (more typically) I’m just too busy to shoot any pics. Yesterday was an exception. We had our GC send out a crew to finish some of the framing yesterday, and I managed to get some photos of (what’s left of) our kitchen:

100_2072.JPG 100_2074.JPG

I also managed to get a picture of the laundry/utility room before the doors were installed:

100_2075.JPG

The stucco foreman came out to look at the project yesterday. He gave us a rather long list of things that needed to be taken care of before he could put up the lath. :( But the good news is that he had his crew set up the scaffolding early so that we could use it to finish sheathing our gables. (That’ll be much easier than hauling sheets of plywood up a pair of ladders!)

Work remaining before rough frame inspection:

  • (us) Finish rough electrical–mostly the kitchen, which I can start now that the kitchen framing is done;
  • (plumber) Finish rough plumbing–water heater T&P hookup, utility sink vent reconnected;
  • (us) Take care of the issues listed by the stucco foreman;
  • (insul.) Insulate the original west wall of the house (insulation crew is scheduled for next Monday);
  • (us) Sheath the wall after insulation is installed (rain forecast for Tuesday, so Barb and I will do this Monday evening);
  • (us) Sheath the rest of the gables (after rough plumbing is finished);
  • (stucco) House wrap and lath for stucco.

We’ve got a busy weekend ahead of us! But hopefully we can be ready for our rough frame inspection by late next week, which would leave us five weeks until Thanksgiving. It’ll be close, but I think we can make it.

02
Oct

Electrical progress

I’ve been spending nearly all of my “free” time working on the wiring. I’ve come to realize the biggest hurdle (for me) with rough electrical: You do all the work on the wiring, yet there’s no outlets to plug into, no lights to switch on, etc. All that stuff has to wait until after drywall! :(

Anyway, here’s the progress made by room/area:

  • Caira’s bedroom: Done except for termination of network/phone lines.
  • Caitlin’s bedroom: Done except for running+termination of network/phone lines.
  • New bathroom: Power run for lights and fan, but a fair bit of work remains to be done.
  • Laundry/utility room: Done except for network/phone feed. (The patch panel will be in the utility room, so all the comm wiring terminates there.)
  • Hallway: Done.
  • Nook: Done.
  • Kitchen: Main (fluorescent) lighting placed and temporarily wired. (Lots left to do!)
  • Dining/game room: West wall (switches, outlets) done.
  • Living room: No high voltage work, still need to run network/phone lines.
  • Great room: West wall (entertainment center) wired, including speaker wires, network/phone wiring. Wall outlets done. Sconce lighting done.
  • Front porch: No progress.
  • Garage: Ceiling outlets (lights, garage door opener) done. Power run to GFCI outlet, but not terminated.
  • Back porch: Coach lights [re-]placed. Still need to wire them and patch the walls where they were originally placed.
  • Quilt shop: Floor outlets done. Outlets on west wall. Quite a bit of work remaining, but the shop is lower priority than the house at this point. (It’s a separate permit, so we don’t need to have it done at the same time as the house.)
  • Attic: Whole-house fan done, FAU done, power (40 A @ 220 V!) run to condenser, attic lights almost finished. Power is run for one attic fan.

The major items on the punch list are (biggest to smallest):

  1. Kitchen: Can’t do much until we fur out the original east wall to line up with the new wall, but we’ll lose our remaining kitchen facilities when we do that. Thus it will probably be the last thing we tackle.
  2. Quilt shop (low priority)
  3. New bathroom: Run power for vanities (2 x 20 A circuits). Determine final layout of vanities, place and wire vanity lights and outlets, wire ceiling lights and exhaust fan.
  4. Great room lighting: We’ll need to remove some of the old joists to make room for can lights and ceiling fan mount, then place and wire the new cans.
  5. Dining/game room: New outlets and network/phone wiring in three original walls, complete with fire blocks–not fun. Replace original ceiling light box with a ceiling fan mount.
  6. Garage: Need to install & wire coach lights flanking roll-up door. Waiting on installation of new personnel door for its light.
  7. Front porch: Two can lights over porch, outlets for Christmas lights (with in-use weatherproof box) at peak of gable.
  8. Attic: Install both attic fans, run power to second one. Finish attic lighting circuit. Test whole-house fan.



November 2008
M T W T F S S
« Oct    
 12
3456789
10111213141516
17181920212223
24252627282930

Tags

abramoff accessibility acetylene activism aerial photo afrofunk aim4tree air america airport express alite alito amtrak andante andy anti failure any browser apache apple applescript arden arcade arden park ariana arnold ashland astronomy attic attika audio avid reader backup baen bart bathroom bbq bee beef begonia bgg bike bike hikers bike journal bikejournal biketalk bill oreilly bittorrent blacklist blog bloggercode blogroll blueberry boardgamegeek boardgames bonjour book bookcrossing boot failure bootcamp borderline chaos bugmenot bush business card cabinetry caira caitlin california candamir caroline carpet cat cateye cdrom celebration cellular phone century cheese chicken chico chimney chinese chipotle chocolate christmas chumby city bikes civilization cjd claire club club fed co op coconut coffee comfort food community computer concord congress conquest conservation consumer reports copyright costco crazybikerchick crepe crock pot cruftbox css csus curl currency custard cvntrak dagoba daniel goetz darwinports datarescue date format death delicious monster democracy now Democrat demolition dessert dickens diff disaster discrimination discworld dishwasher diskwarrior dixie belle dock doors downing street memo drm dryer drywall dump ed burke eff eggs eject election electric car electric truck electrical electricity elvgren email energy efficiency eric meyer esr etext euthanasia facebook family faq faux news feed feedreader fence finder firefox first4internet first amendment fishmeal flash flickr flooring foreign exchange foundation fox and goose framing freebsd freedback fyq garage garden geek geotag geourl gnutar go gonuls google google earth google maps gpl gracenote graywater greek green group concat gtd gunthers gutters gwbush gymnastics hacking halloween handspring hardwood harry potter headmeta high speed photograph high tech inv hoax hobbies hobby hodgins holiday holly home power magazine horcrux houseblogs how to html humor hvac ilovejackdaniels impeach inspection insulation intel internet ipod ipodder iq iraq isight itunes ivins iwantsandy java city javascript joint chiefs joseph jott journalized blue judges cup kctc khs kimkerry kitchen kyocera la salles la times labor landscape laundry law leatherbys legal lego leopard lhc liberal library linkedin ljurban lodi logic logo lungren maaloufs mac macbook mailinator malware map marin markdown mason media media clip media reform meetup metric mexican microsoft mike comfort military milonic mindstorms mlk model railroading modoc hall monterey morning sedition motorcycle movie moving munchkin murray mushroom music mynetflix mysql naked lounge nerd score netflix network new urbanism new year New Yorker nofollow nutella oatmeal obama obcz occidental occupation omni openssl oracle organic osx owp paint pair palast palm panasonic parallels party patch peak adventures peak oil pear pedestrian village perl petaluma php ping pingback pingomatic pingomation pingqueue pirate pl sql planet bike plasma playroom entertainment plugin plugin:preview theme plugin:text control plugin:ultimate tag warrior plumbing podcast podsite politics portupgrade potato powerbook printer programming project gutenberg pryde punk puzzle qiana quilt quilt shop quiz quote r5 records racism radio railroad recent comments recipe redalt remodel resaurant resolution restaurant restore review richmond rio americano robotics roger niello ron montana roof rootkit rss sacbee sacog sacramento sacramento spotlight magazine salad san francisco sandwich santa cruz scam scandal school days scplugin security session report shakespeare shuffle sigma siriradha sitemap snl snopes social social network software soma somafab sonicchicken sonicchicken blog sony spam spam karma spellcheck spinach spirit spoiler etiquette spring hill cheese sql sqlserver stairs standards statcounter stephen king stop loss stucco stunt subversion sudoku superbowl superhero supreme court sushi svn sysadmin tacoma tags plugin takara technology telephone television template terms and conditions textcontrol thai kitchen thanksgiving theater theme theme:borderline chaos theme:elvgren theme:elvgren wordpress google code theme:fluid blue theme:fullwidth theme:head theme:journalized theme:journalized blue theme:psycho theme:redoable theme:sharepoint like theme:simple green theme:spirit theme:steam theme:wuhan theme:yadda theme switcher thomas tigris euphrates tile tinfoil hat toc tofu tower theater training transit transit oriented development tribute u haul uneasy rhetoric university village van zant veterans day video vie viking hobby vote smart w3c wall warboss washer washington post weather web web developer web server wikipedia windows wishlist woodworking wordpress workplace wpblacklist wpgatekeeper wsj yaaarr yard