Remodel [phase 1A](http://sonicchicken.net/blog/wordpress/remodeling-project/project-overview/) (home addition, excluding quilt shop) punch list:
**Living room**
* (N/A, phase 2)
**Entry**
* (Us) Salvage hardwood flooring from entry Done!
* (Us) Install Hardiebacker Done!
* (Rick) Floor tile Done!
* (Us) Finish painting (around front door) Done!
* (Us) Finish electrical Done!
* Wall outlets (2) Done!
* Ceiling light Done!
* (Rick) Grout/caulk floor joints
**Dining/game room**
* (Us) Trim drywall around window
* (Artisan Drywall) Sand down texture in dining/game room
* (Us) Paint
* (Us) Finish electrical
* Ceiling fan (after texture sanding)
* Outlets (3)
* Network/telephone jacks
* Smoke alarm
* (BeautiFloors) Refinish game room floor
**Old bathroom Done!**
* (Moreno Const.) Patch up ceiling Done!
* (rest is N/A, phase 2)
**Great room**
* (Us) Finish electrical
* Ceiling fan (after floor refinishing) Done!
* Reading lights (4) Done!
* Wall outlets (5) Done!
* Speaker wiring jacks Done!
* Network/telephone jacks
* (Rick) Floor tile (continue entryway to back door) Done!
* (BeautiFloors) Fill in hardwood Done!
* (BeautiFloors) Refinish floor Done!
* (Rick) Grout/caulk floor joint
**Kitchen**
* (Mike) Demo old kitchen faucet and drain Done!
* (Mike) Vent new kitchen sink and utility sink (attic work) Done!
* (Us) Install Hardiebacker (move appliances as needed) Done!
* (Rick) Install sink & countertop Done!
* (Rick) Install backsplash (glass tile behind range, ceramic tile elsewhere) Done!
* (Rick) Install floor tile Done!
* (Us) Finish electrical
* Garbage disposal and dishwasher wiring — Check for right-angle plugs on both! Done!
* Countertop outlets (after backsplash tile) Done!
* Pendant lights (5)
* Wine frig wiring Done!
* Hood and blower wiring Done!
* (Us) Install hood (after glass backsplash tile) Done!
* (Us) Install range (after glass backsplash tile) Done!
* (Mike) Finish plumbing — kitchen sink, disposal, dishwasher Done!
* (Eric) Cabinet/tile trim (baseboards, scribe, etc) Done!
* (Us) Install dishwasher Done!
* (Us) Install wine frig (installed, but I can’t level it until we find the feet)
* (Rick) Replace two cracked skirt tiles, install missed skirting, caulk/grout behind GFCI outlet
**Nook Done!**
* (Us) Install Hardiebacker Done!
* (Rick) Floor tile Done!
* (Us) Install ceiling fan Done!
**Laundry/utility room**
* (Us) Install switch- and outlet cover plates Done!
* (Us) Route edges of telecomm backer board Done!
* (Us) Paint backer board Done!
* (Us) Mount backer board Done!
* (Us) Terminate telecomm wiring
* (Us) Install Hardiebacker Done!
* (Rick) Floor tile Done!
**New bathroom Done!**
* (Mike) Bathtub drain Done!
* (Us) Install Hardiebacker Done!
* (Rick) Floor tile Done!
* (Rick) Shower/bath surround tile Done!
* (Moreno Const.) Install medicine cabinets Done!
* (Moreno Const.) Install vanities (after floor tile & medicine cabinets) Done!
* (Mike) Bathtub faucet and shower head Done!
* (Mike) Install toilet Done!
* (Mike) Finish plumbing — bathroom sinks, faucets Done!
* (Us) Finish electrical Done!
* Ceiling lights’ switch Done!
* Exhaust fan switch Done!
* Sconce lights (4) Done!
* Vanity outlets (4) Done!
* Vanity switches (2) Done!
**Bedroom hallway**
* (Us) Install whole-house fan shutter Done!
* (Us) Finish painting Done!
* (Us) Finish electrical Done!
* Wall outlet Done!
* Lights, switches (3) Done!
* Whole-house fan controls Done!
* Smoke alarm Done!
* (Us) Install Hardiebacker Done!
* (Rick) Floor tile Done!
* (BeautiFloors) Bamboo flooring Done!
* (Rick) Grout/caulk floor joint
**Caitlin’s bedroom**
* (Caitlin) Paint closet Done!
* (Us) Finish electrical
* Run network and telephone wiring, terminate
* Wall outlets (5) Done!
* Smoke alarm Done!
* Ceiling fan (after HVAC grills and returns) Done!
* Install closet lights Done!
* (BeautiFloors) Bamboo flooring Done!
* (Moreno Const.) Hang closet doors Done!
**Caira’s bedroom**
* (Caira) Finish painting (2 walls, closet) Done!
* (Us) Finish electrical
* Wall outlets (5) Done!
* Smoke alarm Done!
* Ceiling fan (after HVAC grills and returns) Done!
* Install closet lights Done!
* Network and telephone jacks
* (Moreno Const.) Adjust bedroom door
* (BeautiFloors) Bamboo flooring Done!
* (Moreno Const.) Hang closet doors Done!
**Garage**
* (Us) Finish painting (cutting in, touch-up)
* (Moreno Const.) Step(s) for garage/utility room door Done!
* (Us) Garage coach lights (2) Done!
* (Us) Cover ceiling outlets (3) Done!
* (Us) Install fluorescent lights (2)
* (Us) Garage personnel door light and switch Done!
* (Moreno Const.?) Install attic stairs
**Attic**
* (Us) Install attic fans (2) Done!
* (Us) Verify whole-house fan installation and wiring Done!
* (Us) Clean up wiring for attic lights and switches Done!
**Exterior**
* (Alpha Services HVAC) Install AC condensor, wiring Done!
* (mason) Extend chimney, install counterflashing and chimney cover/spark arrestor Done!
* (Louis) Install downspouts, re-seal gutters Done!
* (Us) Paint old front door Done!
* (Us) Doorbell
* (Us) Front porch outlet Done!
* (Us) Christmas light outlet Done!
* (Us) Wall outlet on east side of house Done!
* (Us) Back door coach lights (3) Done!
* (Us) Install louvers for attic fans
* (Mike?) Hose bib on east side of house
* (Mike?) Gas valve for BBQ
* (ACMS?) Re-sweat landscape ball valve so handle operates vertically
* (Moreno Const.) Landing and steps for back door Done!
* (Us) GFCI outlet for BBQ Done!
* (Us) Redo right side of electrical panel such that door closes smoothly Done!
* (Us) Label electrical panel
* (Us) Paint pop-outs
* (Moreno Const.) AC condensor pad Done! (Other concrete flatwork is phase 4.)
* (Us) Rebuild fence and gate on east side (personnel door behind fence) — phase 4
* (?) New gate for shop driveway — phase 4
**Interior finish work**
* (Alpha Services HVAC) Install grills and returns Done!
* (Us) Door trim
* (Us) Baseboards
* (Us) Window trim
* (Us) Touch-up painting
Pingback: Punch list at SonicChicken blog
Pingback: Salvaging hardwood floors, other progress on the house at SonicChicken blog
Pingback: Remodel update at SonicChicken blog
Pingback: One week ’til final inspection! at SonicChicken blog